Achievements
October 2023 (Month 1) :
- Start of the project and Kick-off meeting (MS1) organized.
December 2023 (Month 3):
- Project Management Plan (D8.1) completed.
- The project website (MS2) is operational, the visual identity developed, and the social media-related accounts created.
January 2024 (Month 4):
- Technical drawing of the bearing system (D1.2) completed.
- Detailed drawing – absorber sliding system (D1.3) completed.
- Technical drawing of collector foundation (D1.5) completed
February 2024 (Month 5):
- Design freeze “drive and tracking control” (MS3) achieved.
- Detailed drawing of collector drive system (D1.4) completed.
- Piping and instrumentation diagram (D1.9) completed.
March 2024 (Month 6):
- Isometric drawing of connection pipes (D1.8) completed.
- Design freeze “collector hardware” (MS4) achieved.
- Detailed drawing – collector structure (D1.1)
- Plan for Dissemination and Exploitation including Communication Activities (D7.2)
- Data Management Plan (D7.4) completed.
April 2024 (Month 7):
- Design freeze “assembly jig” (MS5)
- Technical drawing assembly jig (D1.7)
- Stakeholders Database (D7.3)
June 2024 (Month 9):
- Design report – automatic mirror washer (D1.10)
July 2024 (Month 10):
- Detailed drawing of composite mirrors (D1.6)
November 2024 (Month 14):
- Assembly jig parts manufacturing report (D2.1)
- Functional description of mirror washer (D2.5)
December 2024 (Month 15):
- Collector tracking software finished (MS8)
- Tracking software programme (D2.4)
January 2025 (Month 16):
- Construction permit granted (MS7)
- Construction application (D2.6)