October 2023 (Month 1) :

  • Start of the project and Kick-off meeting (MS1) organized.

December 2023 (Month 3):

  • Project Management Plan (D8.1) completed.
  • The project website (MS2) is operational, the visual identity developed, and the social media-related accounts created.

January 2024 (Month 4):

  • Technical drawing of the bearing system (D1.2) completed.
  • Detailed drawing – absorber sliding system (D1.3) completed.
  • Technical drawing of collector foundation (D1.5) completed

February 2024 (Month 5):

  • Design freeze “drive and tracking control” (MS3) achieved.
  • Detailed drawing of collector drive system (D1.4) completed.
  • Piping and instrumentation diagram (D1.9) completed.

March 2024 (Month 6):

  • Isometric drawing of connection pipes (D1.8) completed. 
  • Design freeze “collector hardware” (MS4) achieved.
  • Detailed drawing – collector structure (D1.1)
  • Plan for Dissemination and Exploitation including Communication Activities (D7.2)
  • Data Management Plan (D7.4) completed.

April 2024 (Month 7):

  • Design freeze “assembly jig” (MS5)
  • Technical drawing assembly jig (D1.7)
  • Stakeholders Database (D7.3)

June 2024 (Month 9):

  • Design report – automatic mirror washer (D1.10)

July 2024 (Month 10):

  • Detailed drawing of composite mirrors (D1.6)

November 2024 (Month 14):

  • Assembly jig parts manufacturing report (D2.1)
  • Functional description of mirror washer (D2.5)

December 2024 (Month 15):

  • Collector tracking software finished (MS8)
  • Tracking software programme (D2.4)

January 2025 (Month 16):

  • Construction permit granted (MS7)
  • Construction application (D2.6)